Texas · Transmission & distribution utility (electric) with separate gas utility · LAST CHECKED 2026-11-13

CenterPoint Energy Houston Electric: generator, battery backup & CPAP rules

Service area: Greater Houston including Katy, Sugar Land, The Woodlands, Pearland, Baytown and Galveston

Short answer: Meter collars — Not accepted. Medical program — Texas Critical Care / Chronic Condition designation. Backup battery program — none for medical customers.
CenterPoint (Houston) at a glance
Utility typeTransmission & distribution utility (electric) with separate gas utility
StateTexas (TX)
ZIP prefixes770, 772, 773, 774, 775
Meter collar policyNot accepted
External disconnect ruleCenterPoint must approve a standby generator's transfer switch before work begins: manual and open-transition switches go through its Transfer Switch Portal, and closed-transition switches need approval from its Distributed Generation department.
Local gas providerCenterPoint Energy (gas)
Medical registryTexas Critical Care / Chronic Condition designation
Battery / generator rebateNone listed for medical customers
Verified official sources8 (checked 2026-11-13)

Why CenterPoint (Houston) prohibits meter collars & what to use instead

Not accepted

CenterPoint's Evaluated Metering Equipment List rates meter-socket adaptors (MSAs) from all manufacturers as unacceptable (evaluated December 13, 2022), including adaptors for automatic transfer, microgrid interconnect devices, distributed energy resources, EV chargers, load management and surge protection. Its Service Standards (Article 215.5) say customers may not install or use any transfer switch on the CenterPoint side of the meter or between the meter and the meter socket jaws, and only CenterPoint's agents and persons authorized by law may remove a CenterPoint meter seal or lock.

CenterPoint (Houston) lockable disconnect requirements for generators and batteries

CenterPoint must approve a standby generator's transfer switch before work begins: manual and open-transition switches go through its Transfer Switch Portal, and closed-transition switches need approval from its Distributed Generation department. The application asks for the ESID, a one-line diagram, the transfer switch make and model, the electrician's license number and the generator size. Permanently installed standby generators must be on the customer side of the meter, behind a service-entrance-rated device that prevents tying the running generator into CenterPoint's system. For inverter systems that run in parallel, such as solar or batteries, the AC disconnect must be lockable, visible, readily accessible and have an external handle, and is typically within 10 feet of the meter; if it is farther, a placard within 10 feet of the meter must show where it is.

CenterPoint (Houston) gas meter upgrades for standby generators

Gas utility: CenterPoint Energy (gas)

No published fee. CenterPoint says a gas generator may need an upgraded meter or an additional service line and meter; for smaller jobs you request the upgrade with its online meter upgrade tool once the appliances are in place and ready to connect. Projects with a total gas load over 550 CFH at standard delivery pressure need a formal design review, which can take longer.

Quick gas load check

Gas appliances that may run at the same time

Assumes about 14,000 BTU/hr per generator kW at full load and 1,000 BTU per cubic foot of gas; your generator's spec sheet value wins. For dryers, other appliances or a spec-sheet value, use the full gas meter calculator.

Read how gas meter sizing works.

CenterPoint (Houston) medical program for CPAP, BiPAP and oxygen users

Program
Texas Critical Care / Chronic Condition designation
What it provides
Advance notice of planned outages, plus the added disconnection protections in the Texas PUC rule (critical care). No bill discount; CenterPoint says registration does not guarantee uninterrupted power or priority restoration during unplanned outages. You apply through your retail electric provider.
CPAP / BiPAP
Not named in the rule; qualifies only if a physician certifies dependence on an electric medical device to sustain life (critical care) or a serious condition requiring one (chronic condition).
Renewal
Under the PUC rule, critical care: every 2 years; chronic condition: 90 days, or up to 1 year for a lifelong condition. CenterPoint asks customers to update their registration annually or when their medical needs change.

Backup power options for CenterPoint (Houston) medical customers

We found no backup battery or generator program for medical customers at CenterPoint (Houston). No CenterPoint backup battery or generator program for households was found; the CenterPoint Energy Foundation's Community Generator Donation Program funds generators for community facilities chosen with local officials, not homes.

Plan your own backup: size a battery to your device's wattage and the outage length you want to cover, or pair a generator with a transfer switch your utility accepts. Our CPAP power outage guide walks through the options.

Frequently asked questions

CenterPoint (Houston) does not accept meter collars — can I use a transfer switch or interlock instead?

CenterPoint's Evaluated Metering Equipment List rates meter-socket adaptors (MSAs) from all manufacturers as unacceptable (evaluated December 13, 2022), including adaptors for automatic transfer, microgrid interconnect devices, distributed energy resources, EV chargers, load management and surge protection. Its Service Standards (Article 215.5) say customers may not install or use any transfer switch on the CenterPoint side of the meter or between the meter and the meter socket jaws, and only CenterPoint's agents and persons authorized by law may remove a CenterPoint meter seal or lock. Disconnect requirements: CenterPoint must approve a standby generator's transfer switch before work begins: manual and open-transition switches go through its Transfer Switch Portal, and closed-transition switches need approval from its Distributed Generation department. The application asks for the ESID, a one-line diagram, the transfer switch make and model, the electrician's license number and the generator size. Permanently installed standby generators must be on the customer side of the meter, behind a service-entrance-rated device that prevents tying the running generator into CenterPoint's system. For inverter systems that run in parallel, such as solar or batteries, the AC disconnect must be lockable, visible, readily accessible and have an external handle, and is typically within 10 feet of the meter; if it is farther, a placard within 10 feet of the meter must show where it is.

How do I get a bigger CenterPoint Energy meter for a standby generator?

No published fee. CenterPoint says a gas generator may need an upgraded meter or an additional service line and meter; for smaller jobs you request the upgrade with its online meter upgrade tool once the appliances are in place and ready to connect. Projects with a total gas load over 550 CFH at standard delivery pressure need a formal design review, which can take longer.

Does Texas Critical Care / Chronic Condition designation guarantee priority restoration during an outage?

Advance notice of planned outages, plus the added disconnection protections in the Texas PUC rule (critical care). No bill discount; CenterPoint says registration does not guarantee uninterrupted power or priority restoration during unplanned outages. You apply through your retail electric provider. CPAP / BiPAP: Not named in the rule; qualifies only if a physician certifies dependence on an electric medical device to sustain life (critical care) or a serious condition requiring one (chronic condition).

How CenterPoint (Houston) compares with other Texas utilities

UtilityMeter collarsMedical programBattery program
CenterPoint (Houston) TX Not accepted Texas Critical Care / Chronic Condition designation —
Oncor TX Not accepted Texas Critical Care / Chronic Condition designation —
Austin Energy TX Accepted Medically Vulnerable Registry None for medical customers (general: Power Partner Battery)
Pedernales Electric Co-op TX No published rule found Medical Necessity Program —